D.C. streams face major threats, but restoration work is underway - The Washington Informer
The District, a city built at the meeting point of two rivers, has lost about 70% of the smaller waterways that defined its geography 125 years ago. Over the past decade, D.C. has begun working to protect some of the streams and creeks that still exist today, many of which face major threats.
Late last month, federal and local officials — along with a few D.C. activists — took a tour of three streams in Ward 7, each of which is in different stages of restoration work.
Site 1: Fort Dupont Park – Awaiting Restoration
The Fort Dupont stream restoration project, which hasn't yet started construction, received $2.5 million last year from the Biden administration's America the Beautiful Challenge grant program. Last month's tour coincided with the announcement of the 2024 request for proposals; in this year's cycle, the administration expects to award up to $119 million in grants to communities around the country.

Josh Burch, DOEE's stream protection specialist, describes the problem to the group. "It's like taking a firehose and pointing it at sand," he explained. "When it rains out, the Anacostia River looks like coffee with milk in it, and it's all that sediment stirred up." (Kayla Benjamin/The Washington Informer)
" data-medium-file="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?fit=300%2C225&ssl=1" data-large-file="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?fit=780%2C585&ssl=1" src="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332.jpeg?resize=780%2C585&ssl=1" alt="Josh Burch, DOEE's stream protection specialist, describes the problem to the group. "It's like taking a firehose and pointing it at sand," he explained. "When it rains out, the Anacostia River looks like coffee with milk in it, and it's all that sediment stirred up." (Kayla Benjamin/The Washington Informer)" class="wp-image-1202768" srcset="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=1024%2C768&ssl=1 1024w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=300%2C225&ssl=1 300w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=150%2C113&ssl=1 150w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=768%2C576&ssl=1 768w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=1536%2C1152&ssl=1 1536w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=2048%2C1536&ssl=1 2048w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=1200%2C900&ssl=1 1200w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=800%2C600&ssl=1 800w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=600%2C450&ssl=1 600w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=400%2C300&ssl=1 400w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=200%2C150&ssl=1 200w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?resize=1568%2C1176&ssl=1 1568w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-scaled.jpeg?w=2340&ssl=1 2340w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3332-1024x768.jpeg?w=370&ssl=1 370w" sizes="(max-width: 780px) 100vw, 780px" data-recalc-dims="1">Site 2: Fort Davis Tributary – Under Construction
In the woods along Park Drive SE near Branch Avenue SE, construction is underway to address major stream bank erosion, which has created a massive drop not far from the edge of the road. The project, which will build a series of "stair steps" designed to slow down and spread out the flow of water, started construction in January and is expected to finish by June 1. (Robert R. Roberts/The Washington Informer)
" data-medium-file="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?fit=300%2C187&ssl=1" data-large-file="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?fit=780%2C487&ssl=1" src="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149.jpg?resize=780%2C487&ssl=1" alt="In the woods along Park Drive SE near Branch Avenue SE, construction is underway to address major stream bank erosion, which has created a massive drop not far from the edge of the road. The project, which will build a series of "stair steps" designed to slow down and spread out the flow of water, started construction in January and is expected to finish by June 1. (Robert R. Roberts/The Washington Informer)" class="wp-image-1202769" srcset="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=1024%2C639&ssl=1 1024w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=300%2C187&ssl=1 300w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=150%2C94&ssl=1 150w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=768%2C479&ssl=1 768w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=1536%2C959&ssl=1 1536w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=2048%2C1279&ssl=1 2048w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=1200%2C749&ssl=1 1200w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=1568%2C979&ssl=1 1568w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?resize=400%2C250&ssl=1 400w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-scaled.jpg?w=2340&ssl=1 2340w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8149-1024x639.jpg?w=370&ssl=1 370w" sizes="(max-width: 780px) 100vw, 780px" data-recalc-dims="1">In the woods along Park Drive SE near Branch Avenue SE, construction is underway to address major stream bank erosion, which has created a massive drop not far from the edge of the road. The project, which will build a series of "stair steps" designed to slow down and spread out the flow of water, started construction in January and is expected to finish by June 1. (Robert R. Roberts/The Washington Informer)
" data-medium-file="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?fit=300%2C200&ssl=1" data-large-file="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?fit=780%2C519&ssl=1" src="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127.jpg?resize=780%2C519&ssl=1" alt="In the woods along Park Drive SE near Branch Avenue SE, construction is underway to address major stream bank erosion, which has created a massive drop not far from the edge of the road. The project, which will build a series of "stair steps" designed to slow down and spread out the flow of water, started construction in January and is expected to finish by June 1. (Robert R. Roberts/The Washington Informer)" class="wp-image-1202770" srcset="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=1024%2C682&ssl=1 1024w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=300%2C200&ssl=1 300w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=150%2C100&ssl=1 150w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=768%2C511&ssl=1 768w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=1536%2C1022&ssl=1 1536w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=2048%2C1363&ssl=1 2048w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=1200%2C799&ssl=1 1200w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=1568%2C1044&ssl=1 1568w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?resize=400%2C266&ssl=1 400w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-scaled.jpg?w=2340&ssl=1 2340w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/DSC8127-1024x682.jpg?w=370&ssl=1 370w" sizes="(max-width: 780px) 100vw, 780px" data-recalc-dims="1">Brenda Mallory, chair of the White House Council on Environmental Quality. "One of my favorite parts of my job is really being able to go out into the communities and see how people are energized by what these funds can do," Mallory said. (Kayla Benjamin/The Washington Informer)
" data-medium-file="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?fit=225%2C300&ssl=1" data-large-file="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?fit=768%2C1024&ssl=1" src="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354.jpeg?resize=768%2C1024&ssl=1" alt="Brenda Mallory, chair of the White House Council on Environmental Quality. "One of my favorite parts of my job is really being able to go out into the communities and see how people are energized by what these funds can do," Mallory said. (Kayla Benjamin/The Washington Informer)" class="wp-image-1202771" srcset="https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=768%2C1024&ssl=1 768w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=225%2C300&ssl=1 225w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=113%2C150&ssl=1 113w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=1152%2C1536&ssl=1 1152w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=1536%2C2048&ssl=1 1536w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=900%2C1200&ssl=1 900w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=600%2C800&ssl=1 600w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=450%2C600&ssl=1 450w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=300%2C400&ssl=1 300w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=150%2C200&ssl=1 150w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=1200%2C1600&ssl=1 1200w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=1568%2C2091&ssl=1 1568w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?resize=400%2C533&ssl=1 400w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-scaled.jpeg?w=1920&ssl=1 1920w, https://i0.wp.com/www.washingtoninformer.com/wp-content/uploads/2024/03/IMG_3354-768x1024.jpeg?w=370&ssl=1 370w" sizes="(max-width: 768px) 100vw, 768px" data-recalc-dims="1">Site 3: Branch Avenue Project – Completed


According to Burch, some of the waterway's human neighbors appreciate the change, too.
"This is the anecdotal stuff, it's not scientific — but one of the things that residents like about stream restorations is [that] they can hear the stream flowing," he said.